CLEAN · Theory of Constraints
How do I find the bottleneck?
Three ways, from looking to calculating. Same question: which step sets how much the whole delivers?
The law
One link sets the pace
In a chain of steps that wait on each other, one step locks the pace of the whole. That step is the bottleneck. Throughput is how many finished items the process delivers to the customer per day. That number cannot exceed what that one step can handle.
Speeding up elsewhere grows the pile and the cost. Finished output stays the same.
You find that step in three ways. Looking gives a first guess. The hour-test checks it. The maths gives the number.
- Look — where does work pile up?
- The hour-test — does the customer get more?
- The maths — hours divided by touch time, next to demand.
1 · Look
Where work piles up
Walk the process and find the largest pile. On a shop floor it sits before one machine. In an office it is an inbox, a “waiting for” status, or a list that never shrinks.
The pile sits in front of the constraint. Steps after it wait for work. Steps before it feed faster than the constraint can take.
This takes a few minutes. You do not need a spreadsheet.
2 · The hour-test
Does the customer get more?
Give one step one extra hour: another pair of hands, or an hour without interruption.
Does the customer receive more finished work? Then this is the bottleneck.
Does only the pile before the next step grow? Then the bottleneck sits further downstream. The same hour on that step does give the customer something.
This is the definition. Use the test after you have done the maths as well.
3 · The maths
Capacity next to demand
For a repeating process, a capacity comparison is sharpest. Sketch three or four steps. Use touch time — the time someone actually holds the work — and available hours.
Capacity (items per day) = available hours ÷ touch time per item.
Available hours = FTE × productive hours per day.
Example. A request flows through Analyse, Process, and Finish. Fifteen items arrive per day. Each FTE has 6 productive hours.
| Step | FTE | Touch time | Capacity | At 15 / day |
|---|---|---|---|---|
| Analyse | 2 | 0.5 h | 24 / day | 9 spare |
| Process bottleneck | 3 | 2 h | 9 / day | 6 short |
| Finish | 1 | 0.5 h | 12 / day | 3 short |
Process lets 9 items through per day while 15 arrive. Finish has one person and still more room: 12 per day, a shortfall of 3. The step with the fewest people and the bottleneck are two different steps here. The largest shortfall wins.
An extra person for one day on Process yields 6 hours — 3 more items to the customer. The same person for a day on Analyse only grows the pile before Process. The customer receives nothing extra. Automating Analyse up to 40 per day leaves throughput at 9.
Touch time and lead time
Where work sits still
Touch time is the time someone works the item. Lead time is that time plus waiting: a hand-off, a calendar, an approval.
The longest lead time shows where work sits still. The maths shows which step bounds throughput. Those two often point to different places.
When every step still has room
A policy, or the market
A policy. Everyone still has time, yet work waits on a weekly steering group, a mandatory batch, or the rule that nobody may sit idle. Extra FTE leaves throughput unchanged. Changing that rule raises throughput.
The market. Every step can do 20 per day, demand is 8, and there is no pile. The constraint sits with the customer. Working faster inside the process then leaves throughput flat. A shorter, reliable lead time can unlock demand — then lead time is the lever.
After finding it
Bottleneck first
Remove interruptions at the bottleneck, let that step finish what it holds, and keep work ready in front of it. Keep other steps slightly roomier so a stumble does not idle the constraint. Automate on the bottleneck, or on what feeds or protects it.
Article: Find the bottleneck in 3 steps · Back to the CLEAN sequence