Find the bottleneck in 3 steps
Look, hour test, raise the pace. Same question: which link sets how much the whole delivers?
The iron law
One link sets the pace
Every workstation puts in effort. Flow still does not rise of its own accord. Working efficiently everywhere is not the same as results for the customer.
In a chain of steps that wait on each other, one link sets the pace of the whole. That is an iron law. That link is the bottleneck. Every process has one — in the office and on the shop floor. You cannot escape it, and that is exactly where quick improvement starts.
Speeding up elsewhere grows the pile and the cost. Finished work to the customer stays the same.
Why you miss it
Single-piece flow hides the bottleneck
When you run single-piece flow from LEAN, you no longer see the bottleneck. No piles appear to give it away. Yet it is still there. The law still holds: one link still sets how much the whole delivers.
Step 1
Look — where does work pile up?
Walk the process and find where work sits still. On a shop floor that is often the largest pile in front of one machine. In an office: an inbox, a “waiting for” status, or a list that never shrinks.
The pile sits in front of the bottleneck, not after it. Steps downstream wait for work. Steps upstream feed faster than the bottleneck can take. This takes a few minutes. You do not need a spreadsheet.
Step 2
The hour test — does the customer get more?
Give one step one extra hour: another pair of hands, or an hour without interruption.
Does the customer receive more finished work? Then you have it: this is the bottleneck. Does only the pile before the next step grow? Then the bottleneck sits further downstream. The same extra hour on that later step does give the customer something.
Step 3
Raise the pace — until one station cannot keep up
If you run single-piece flow, you see no piles. Raise the line speed step by step — the takt time — until one station cannot keep up. That is your bottleneck. There you break single-piece flow: that link needs room or a buffer so the bottleneck can keep working.
Where piles are visible you can also calculate: available hours divided by the time someone actually holds the work, next to demand. The largest shortfall names the bottleneck. A worked example is on How do I find the bottleneck?
After that
Bottleneck first, then LEAN
Theory of Constraints restores the order. First find the bottleneck and fully exploit it: remove interruptions, let that step finish what it holds, and keep work ready in front of it. Then bring LEAN tools and thinking to bear at and around that bottleneck — not as an “efficiency everywhere” campaign.
That is Constraint-led LEAN, or CLEAN for short. You keep the toolkit. You change the sequence.